Data 393 Power Infrastructure Maintenance

*** Please be noted that this maintenance will only affect clients which has their hosting services hosted in our US servers at Data393 data center with the IP range of 72.18.131.0/24 - 72.18.132.0/24. Users which has their hosting account hosted in Malaysia is not affected by this maintenance.

On Thursday, November 16, 2006 Data393 (our data center facilities provider) will be performing some essential power infrastructure maintenance that will result in downtime for certain servers. During that evening, we will have three separate maintenance windows open, one for each area impacted by the maintenance work.

F10 MAINTENANCE WINDOW
==================
Date: 16-Nov-2006
T ime: 9:00PM – 10:00PM MST
Purpose of Work: Upgrade to power infrastructure
Impact of Work: Loss of power
Description of Work: During this maintenance Window, Data393 will be relocating some of our power circuits to a different branch of their power distribution infrastructure. During this maintenance window, we will be cleanly shutting down all servers, moving the power circuits, and then powering all servers back up in a controlled manner. We anticipate that it will take Data393 approximately 15-20 minutes to move the power circuits. The rest of the maintenance window has been allocated so that we have enough time to cleanly power off the servers and power them back on.

F13 MAINTENANCE WINDOW
====================
Date: 16-Nov-2006
Time: 9:45PM – 10:45PM MST
Purpose of Work: Upgrade to power infrastructure
Impact of Work: Loss of power
Description of Work: During this maintenance Window, Data393 will be relocating our power circuits to a different branch of their power distribution infrastructure. During this maintenance window, we will be cleanly shutting down all servers, moving the power circuits, and then powering all servers back up in a controlled manner. We anticipate that it will take Data393 approximately 15-20 minutes to move the power circuits. The rest of the maintenance window has been allocated so that we have enough time to cleanly power off the servers and power them back on.

CAGE MAINTENANCE WINDOW
=====================
Date: 16-Nov-2006
Time: 11:00PM – 2:00AM MST
Purpose of Work: Upgrade to power infrastructure
Impact of Work: Loss of power
Description of Work: During this maintenance Window, Data393 will be relocating the power distribution panel that powers all of our servers in our private cage. During this maintenance window, we will be cleanly shutting down all servers, moving the power panel, and then powering all servers back up in a controlled manner. We estimate that it will take 60-75 minutes to move the power panel. The rest of the maintenance window has been allocated so that we have enough time to cleanly power off the servers and power them back on.

With Best Regards,

Support Team
-------------------
Technical Department
Exa Bytes Network Private Limited
Web: http://www.exabytes.com
Email: support@exabytes.com
Helpdesk: http://support.exabytes.com/help/