[COMPLETED] US: Scheduled server maintenance - Critical Windows Update (Phase 3)

Date: 6 March 2013
Time: 11:46 AM MST

The maintenance is completed.

========================================================

Date: 6 March 2013

Time: 12:48 AM MST
ETA : 30 minutes

All server done except Mustang which is still running the updates.

========================================================


Date: 5 March 2013

Time: 11PM GMT-0700
ETA : 2hrs

Maintenance details:
We will performing windows update and reboot exercise for listed servers below:

Galaxy        72.18.131.235
Spirit        72.18.132.204
Starlifter    72.18.132.198
Blackbird    72.18.131.170
Thunderbolt    72.18.131.38
Raven        72.18.132.150
Strikeeagles     72.18.131.43
Mustang        72.18.132.174
MachuPicchu 72.18.130.10
ChristRedeemer 72.18.130.7
GreatWallChina 72.18.130.6
Colusseum 72.18.130.12
Newton 72.18.131.114


Maintenance effect:
During the maintenance time frame, window services such as web and ftp will not be available. 

Best Regards,

Support Team
......................................
Technical Support Department